A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are
The correct answer is B. Program risk. During program initiation, the focus is on establishing the program's business case and high-level attributes: program benefits (why it exists), program scope (what it will deliver), and its link to organizational strategy (how it aligns with business goals). Detailed program ris
Question
A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
Options
- AProgram benefits
- BProgram risk
- CProgram scope
- DLink to organizational strategy
How the community answered
(21 responses)- A5% (1)
- B90% (19)
- D5% (1)
Explanation
During program initiation, the focus is on establishing the program's business case and high-level attributes: program benefits (why it exists), program scope (what it will deliver), and its link to organizational strategy (how it aligns with business goals). Detailed program risk identification and analysis is a planning-phase activity, not an initiation activity. While high-level risks may be briefly acknowledged, formal risk identification belongs in planning.