nerdexam
PMI

PGMP · Question #203

You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following

The correct answer is D. Quality control measurements. According to the PMBOK Guide, the inputs to the Close Project or Phase process are: the Project Management Plan, Accepted Deliverables, and Organizational Process Assets. Quality control measurements are an output of the Control Quality process, not an input to the Close Project

Program Life Cycle Management

Question

You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?

Options

  • AProject management plan
  • BOrganizational process assets
  • CProject deliverables
  • DQuality control measurements

How the community answered

(21 responses)
  • A
    5% (1)
  • C
    5% (1)
  • D
    90% (19)

Explanation

According to the PMBOK Guide, the inputs to the Close Project or Phase process are: the Project Management Plan, Accepted Deliverables, and Organizational Process Assets. Quality control measurements are an output of the Control Quality process, not an input to the Close Project process. They are used during project execution to monitor and verify quality, not during formal project closure. The project management plan, organizational process assets, and project deliverables (accepted deliverables) are all legitimate inputs used to properly close a project.

Topics

#Project Closure#PMBOK Processes#Process Inputs#Close Project or Phase

Community Discussion

No community discussion yet for this question.

Full PGMP Practice