PGMP · Question #202
Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an ex
The correct answer is A. Weather. An assumption is a factor that is considered to be true, real, or certain for planning purposes without proof or demonstration. Weather is an assumption because you are presuming certain weather conditions will (or will not) occur during construction - it is uncertain and unconfi
Question
Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?
Options
- AWeather
- BDeadlines for project milestones
- CA predetermined program budget
- DBuilding codes
How the community answered
(27 responses)- A93% (25)
- B4% (1)
- D4% (1)
Explanation
An assumption is a factor that is considered to be true, real, or certain for planning purposes without proof or demonstration. Weather is an assumption because you are presuming certain weather conditions will (or will not) occur during construction - it is uncertain and unconfirmed. Deadlines for project milestones and a predetermined program budget are constraints, not assumptions - they are fixed limitations imposed on the project. Building codes are regulatory requirements, which are also constraints the project must comply with, not assumptions.