Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?
Options
- AWeather
- BDeadlines for project milestones
- CA predetermined program budget
- DBuilding codes