PGMP · Question #198
All of the following information is defined in the program statement of work except for which one?
The correct answer is A. Structure of the program management team. This question tests which type of content belongs in a program statement of work versus other program documents.
Question
All of the following information is defined in the program statement of work except for which one?
Options
- AStructure of the program management team
- BProgram requirements for resource competency levels
- CMetrics and qualifications for program acceptance
- DLocation of the program work
How the community answered
(54 responses)- A93% (50)
- B2% (1)
- C4% (2)
- D2% (1)
Why each option
This question tests which type of content belongs in a program statement of work versus other program documents.
The program statement of work defines the work to be performed - scope, deliverables, resource competency requirements, acceptance criteria, and work location - but it does not define the internal organizational structure of the program management team. Team structure and reporting relationships are addressed in the program management plan and program organization charts, not in the SOW.
Resource competency requirements are explicitly included in the program SOW so the performing organization understands the skill levels needed to execute the work.
Metrics and acceptance criteria are included in the SOW to establish a shared agreement between client and performer on what constitutes successful delivery.
The location where program work will be performed is specified in the SOW so all parties understand site and facility expectations.
Concept tested: Program statement of work content
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management