Which of the following documents describes the details for each component in the WBS?

The correct answer is C. WBS dictionary. This question asks which document provides detailed descriptions of each component within the Work Breakdown Structure.

Program Life Cycle Management

Question

Which of the following documents describes the details for each component in the WBS?

Options

  • AWBS detail
  • BRisk register
  • CWBS dictionary
  • DProject charter

How the community answered

(28 responses)
  • B
    7% (2)
  • C
    89% (25)
  • D
    4% (1)

Why each option

This question asks which document provides detailed descriptions of each component within the Work Breakdown Structure.

AWBS detail

'WBS detail' is not a recognized formal project management document - the correct and standard term for this artifact is the WBS dictionary.

BRisk register

The risk register documents identified risks, their probability and impact, and response strategies - it does not describe the content or boundaries of WBS components.

CWBS dictionaryCorrect

The WBS dictionary is the companion document to the WBS that provides detailed information for each WBS component, including scope descriptions, deliverables, acceptance criteria, responsible parties, and cost and schedule data. It ensures all stakeholders share a precise and consistent understanding of every work package and control account.

DProject charter

The project charter authorizes the project and designates the project manager but does not contain granular descriptions of individual WBS elements.

Concept tested: WBS dictionary purpose and content

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#WBS#WBS Dictionary#Scope Management#Program Documentation