PGMP · Question #150
PGMP Question #150: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #150. The question stem and answer options stay visible for context.
Question
You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?
Options
- A$2,656,500
- BThere is not enough information to know.
- C$3,795,000
- D$1,035,000
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.