nerdexam
PMI

PGMP · Question #150

You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has

The correct answer is C. $3,795,000. Using EVM, the program's CPI of approximately 0.909 (from a 10% cost overrun) applied to the BAC of $3,450,000 yields an EAC of $3,795,000.

Program Life Cycle Management

Question

You are the program manager for your organization. Your current program has a budget at completion of $3,450,000 and is expected to last two years. The program is currently 30 percent complete and has spent ten percent more than what it should have to arrive at this point in the program schedule. Based on this information, what is estimate at completion (EAC) for this program?

Options

  • A$2,656,500
  • BThere is not enough information to know.
  • C$3,795,000
  • D$1,035,000

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    14% (3)
  • C
    71% (15)
  • D
    5% (1)

Why each option

Using EVM, the program's CPI of approximately 0.909 (from a 10% cost overrun) applied to the BAC of $3,450,000 yields an EAC of $3,795,000.

A$2,656,500

$2,656,500 does not result from any standard EAC formula applied to the values given in this scenario.

BThere is not enough information to know.

There is sufficient information to calculate EAC - the BAC, percent complete, and cost performance ratio (10% overrun) provide everything needed for the EAC = BAC/CPI formula.

C$3,795,000Correct

EV = 30% x $3,450,000 = $1,035,000. Because the program spent 10% more than planned, AC = $1,035,000 x 1.10 = $1,138,500. CPI = EV/AC = $1,035,000 / $1,138,500 = 0.9091. EAC = BAC / CPI = $3,450,000 / 0.9091 = $3,795,000, confirming option C as correct.

D$1,035,000

$1,035,000 is the earned value (EV) representing 30% of BAC, not the estimate at completion for the entire program.

Concept tested: Estimate at completion calculation using CPI and EVM

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Earned Value Management (EVM)#Estimate at Completion (EAC)#Cost Performance Index (CPI)#Program Financial Management

Community Discussion

No community discussion yet for this question.

Full PGMP Practice