nerdexam
PMI

PGMP · Question #149

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the…

The correct answer is A. Change requests. Change requests are an output of the schedule control process, not an input or tool, so they do not help perform schedule control - they result from it.

Program Control

Question

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Options

  • AChange requests
  • BForecasts
  • CEarned value management
  • DPerformance reports

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    3% (1)
  • D
    10% (3)

Why each option

Change requests are an output of the schedule control process, not an input or tool, so they do not help perform schedule control - they result from it.

AChange requestsCorrect

Schedule control analyzes performance data and produces change requests as outputs when corrective or preventive actions are needed. Because change requests are generated by the process rather than used to perform it, they cannot help the program manager conduct schedule control activities.

BForecasts

Forecasts such as Estimate to Complete (ETC) and Estimate at Completion (EAC) provide predictions of future schedule performance and are valuable inputs used during schedule control analysis.

CEarned value management

Earned value management provides quantitative schedule performance metrics - specifically Schedule Variance (SV) and Schedule Performance Index (SPI) - that directly support schedule control decisions.

DPerformance reports

Performance reports provide current schedule status data including actual dates and variance information, making them an essential input for identifying schedule problems requiring control action.

Concept tested: Schedule control inputs vs. outputs distinction

Source: https://www.pmi.org/pmbok-guide-standards/foundational/program-management

Topics

#Program Schedule Management#Schedule Control#Program Control#Program Performance Domain

Community Discussion

No community discussion yet for this question.

Full PGMP Practice