nerdexam
PMI

PGMP · Question #106

You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program…

The correct answer is A. Program requirements for resource competency levels. The program statement of work defines what the program will deliver and its structure, but resource competency level requirements are not a standard element defined within it.

Program Life Cycle Management

Question

You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

Options

  • AProgram requirements for resource competency levels
  • BStructure of the program management team
  • CMetrics and qualifications for program acceptance
  • DLocation of the program work

How the community answered

(58 responses)
  • A
    93% (54)
  • B
    2% (1)
  • C
    2% (1)
  • D
    3% (2)

Why each option

The program statement of work defines what the program will deliver and its structure, but resource competency level requirements are not a standard element defined within it.

AProgram requirements for resource competency levelsCorrect

The program statement of work describes the program's deliverables, objectives, acceptance criteria, location of work, and the structure of the program management team, but it does not define resource competency requirements. Competency requirements for resources are determined during resource planning activities, not within the scope-defining statement of work. Including resource competency specifications would be outside the intended purpose of this document.

BStructure of the program management team

The structure of the program management team is a standard element included in the program statement of work.

CMetrics and qualifications for program acceptance

Metrics and qualifications for program acceptance are key deliverable criteria and are included in the program statement of work.

DLocation of the program work

The location where program work will be performed is included in the program statement of work as a logistical and scope element.

Concept tested: Contents of a program statement of work

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Program SOW#Program Definition#Program Documentation#Program Planning

Community Discussion

No community discussion yet for this question.

Full PGMP Practice