PGMP · Question #105

Performing quality assurance in a program can result in which one of the following?

The correct answer is D. Change requests. Performing quality assurance reviews can reveal process gaps and nonconformances, which result in change requests as a primary output of that process.

Program Governance

Question

Performing quality assurance in a program can result in which one of the following?

Options

  • AQuality control execution
  • BScope fulfillment
  • CQuality management plan
  • DChange requests

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    5% (2)
  • D
    86% (37)

Why each option

Performing quality assurance reviews can reveal process gaps and nonconformances, which result in change requests as a primary output of that process.

AQuality control execution

Quality control execution is a separate process from quality assurance; it is not an output that results from performing QA.

BScope fulfillment

Scope fulfillment is not a defined output of the quality assurance process in standard program or project management frameworks.

CQuality management plan

The quality management plan is created during planning and serves as an input to quality assurance, not an output produced by it.

DChange requestsCorrect

Quality assurance involves auditing quality requirements and the results of quality control measurements to ensure appropriate quality standards are used. When deficiencies or process improvements are identified, the result is change requests - including recommended corrective actions, preventive actions, or defect repairs. These change requests then feed into integrated change control for disposition.

Concept tested: Outputs of the perform quality assurance process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Quality Assurance#Program Quality Management#Process Outputs#Change Management