PGMP · Question #105
Performing quality assurance in a program can result in which one of the following?
The correct answer is D. Change requests. Performing quality assurance reviews can reveal process gaps and nonconformances, which result in change requests as a primary output of that process.
Question
Performing quality assurance in a program can result in which one of the following?
Options
- AQuality control execution
- BScope fulfillment
- CQuality management plan
- DChange requests
How the community answered
(43 responses)- A7% (3)
- B2% (1)
- C5% (2)
- D86% (37)
Why each option
Performing quality assurance reviews can reveal process gaps and nonconformances, which result in change requests as a primary output of that process.
Quality control execution is a separate process from quality assurance; it is not an output that results from performing QA.
Scope fulfillment is not a defined output of the quality assurance process in standard program or project management frameworks.
The quality management plan is created during planning and serves as an input to quality assurance, not an output produced by it.
Quality assurance involves auditing quality requirements and the results of quality control measurements to ensure appropriate quality standards are used. When deficiencies or process improvements are identified, the result is change requests - including recommended corrective actions, preventive actions, or defect repairs. These change requests then feed into integrated change control for disposition.
Concept tested: Outputs of the perform quality assurance process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok