PFMP · Question #81
Which of the following items are considered as portfolio process assets? (Choose two.)
The correct answer is B. Portfolio performance metrics D. Portfolio budget. Portfolio process assets are management artifacts specific to the portfolio itself, such as performance metrics and budget allocations used to track and govern portfolio execution.
Question
Which of the following items are considered as portfolio process assets? (Choose two.)
Options
- ALessons learned
- BPortfolio performance metrics
- CVision and mission statements
- DPortfolio budget
How the community answered
(69 responses)- A7% (5)
- B90% (62)
- C3% (2)
Why each option
Portfolio process assets are management artifacts specific to the portfolio itself, such as performance metrics and budget allocations used to track and govern portfolio execution.
Lessons learned are organizational process assets at the enterprise level, shared across projects and programs organization-wide, not artifacts that belong exclusively to the portfolio process.
Portfolio performance metrics are a portfolio process asset because they are produced and consumed within the portfolio management process to evaluate how well the portfolio is meeting its objectives, making them an inherent artifact of portfolio execution.
Vision and mission statements are organizational strategic assets that guide the entire enterprise and precede portfolio definition, rather than being generated or maintained within the portfolio process.
Portfolio budget is a portfolio process asset because it represents the financial baseline specific to the portfolio that is used to authorize, track, and control spending across all portfolio components.
Concept tested: Portfolio process assets vs. organizational process assets
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management