You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and…

The correct answer is B. Portfolio updates, Portfolio Management Plan updates, Portfolio Reports. Managing supply and demand in portfolio management produces three key outputs: Portfolio updates (reflecting changes in which projects are included or prioritized), Portfolio Management Plan updates (documenting how supply/demand decisions will be governed going forward), and…

Question

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. What is the expected outcome from managing supply and demand?

Options

  • APortfolio updates, Portfolio Management Plan updates, Portfolio Reports updates, Portfolio
  • BPortfolio updates, Portfolio Management Plan updates, Portfolio Reports
  • CPortfolio updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process
  • DPortfolio updates, Portfolio Management Plan updates, Portfolio Process Assets updates

How the community answered

(47 responses)
  • A
    15% (7)
  • B
    74% (35)
  • C
    6% (3)
  • D
    4% (2)

Explanation

Managing supply and demand in portfolio management produces three key outputs: Portfolio updates (reflecting changes in which projects are included or prioritized), Portfolio Management Plan updates (documenting how supply/demand decisions will be governed going forward), and Portfolio Reports (communicating resource utilization and efficiency status to stakeholders). Option A and C include 'Portfolio' as a standalone item, which is redundant. Option D replaces 'Portfolio Reports' with 'Portfolio Process Assets updates,' but process assets are typically inputs or organizational artifacts, not direct outputs of this specific management activity. The standard PMI framework outputs for this process align with option B.