nerdexam
PMI

PFMP · Question #57

Your company has a joint venture agreement with another company, but the partner companies'management has never shown up in any portfolio oversight meetings. That leads to a lot of pending decisions.

The correct answer is C. Find a solution in the portfolio risk management plan. The non-participation of joint venture partner management in oversight meetings is a risk scenario that should have been identified and addressed within the portfolio risk management plan.

Portfolio Risk Management

Question

Your company has a joint venture agreement with another company, but the partner companies'management has never shown up in any portfolio oversight meetings. That leads to a lot of pending decisions. How do you address this issue?

Options

  • ATalk to the management of the partner company to understand communication requirements
  • BTalk to the investor to escalate the communication issue
  • CFind a solution in the portfolio risk management plan
  • DConsult senior executives

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    82% (23)
  • D
    4% (1)

Why each option

The non-participation of joint venture partner management in oversight meetings is a risk scenario that should have been identified and addressed within the portfolio risk management plan.

ATalk to the management of the partner company to understand communication requirements

While communication with the partner is reasonable, acting ad-hoc without consulting the documented risk response plan bypasses the structured governance approach.

BTalk to the investor to escalate the communication issue

Escalating directly to investors without first following the documented risk management procedures skips the defined governance process.

CFind a solution in the portfolio risk management planCorrect

In portfolio management, stakeholder non-participation - especially from joint venture partners - is a governance risk that should be identified, analyzed, and have response strategies defined in the portfolio risk management plan. The correct action is to consult the existing risk management plan for documented response strategies rather than taking ad-hoc escalation steps, as the plan provides the approved, structured approach to resolving this type of risk event.

DConsult senior executives

Consulting senior executives is an escalation path, but it should only occur after the documented risk management responses have been followed or are insufficient.

Concept tested: Portfolio risk management plan application

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Risk Management#Stakeholder Engagement#Portfolio Governance#Decision Making

Community Discussion

No community discussion yet for this question.

Full PFMP Practice