PFMP · Question #24

You are developing a portfolio risk management plan. Which inputs do you need? (Choose two.)

The correct answer is A. Portfolio management plan C. Portfolio process assets. Developing a portfolio risk management plan requires the overall portfolio management plan for context and portfolio process assets for templates and historical risk data.

Portfolio Risk Management

Question

You are developing a portfolio risk management plan. Which inputs do you need? (Choose two.)

Options

  • APortfolio management plan
  • BPortfolio strategic plan
  • CPortfolio process assets
  • DPortfolio

How the community answered

(32 responses)
  • A
    88% (28)
  • B
    9% (3)
  • D
    3% (1)

Why each option

Developing a portfolio risk management plan requires the overall portfolio management plan for context and portfolio process assets for templates and historical risk data.

APortfolio management planCorrect

The portfolio management plan provides the governance framework, risk thresholds, and management approach that the risk management plan must align with.

BPortfolio strategic plan

The portfolio strategic plan informs high-level direction but is not a direct input to developing the risk management plan.

CPortfolio process assetsCorrect

Portfolio process assets supply risk management templates, historical risk records, and organizational policies that inform how risks will be identified and managed.

DPortfolio

The portfolio itself (the collection of components) is not listed as a formal input to the risk management planning process.

Concept tested: Inputs to portfolio risk management planning

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Risk Management#Portfolio Planning#PMI Process Inputs