The correct answer is C: Updating the communications plan. See the full explanation below for the reasoning.

Communication Management

Question

A portfolio manager is initiating a new portfolio that has a significant organizational change management component. The project team believes that maintaining stakeholder engagement will be key to successful benefits realization. Which action will be most helpful to the portfolio manager in ensuring stakeholder engagement?

Options

  • APreparing a responsible, accountable, consulted, and informed (RACI) chart
  • BPerforming a strengths, weaknesses, opportunities, and threats (SWOT) analysis
  • CUpdating the communications plan
  • DDistributing a portfolio dashboard regularly

Topics

#Stakeholder Engagement#Communications Management#Portfolio Planning#Organizational Change