Which items should be considered when determining the performance status of the portfolio?

The correct answer is A. Priority and alignment with corporate targets. Portfolio performance status is determined by evaluating component priority and alignment with corporate strategic targets, not by operational project-level metrics.

Strategic Alignment

Question

Which items should be considered when determining the performance status of the portfolio?

Options

  • APriority and alignment with corporate targets
  • BReturn on investment and resources capacity
  • CSunk cost and earned value
  • DPlanned budget and schedule performance

How the community answered

(47 responses)
  • A
    89% (42)
  • B
    2% (1)
  • C
    6% (3)
  • D
    2% (1)

Why each option

Portfolio performance status is determined by evaluating component priority and alignment with corporate strategic targets, not by operational project-level metrics.

APriority and alignment with corporate targetsCorrect

Portfolio performance is measured at the strategic level, meaning the key indicators are whether portfolio components are appropriately prioritized and whether they are delivering value aligned with corporate strategic goals. Priority ensures resources are directed toward the most strategically valuable components, and alignment with corporate targets confirms the portfolio is achieving its intended strategic purpose. These are the distinguishing performance measures of portfolio management versus project or program management.

BReturn on investment and resources capacity

Return on investment and resource capacity are important considerations at the component level but do not capture the portfolio-level strategic performance status.

CSunk cost and earned value

Sunk cost and earned value are project management financial metrics that measure cost efficiency at the component level, not portfolio strategic performance.

DPlanned budget and schedule performance

Planned budget and schedule performance are operational project metrics; while useful inputs, they do not represent the portfolio-level performance indicators tied to strategic objectives.

Concept tested: Portfolio performance measurement against strategic goals

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Performance#Strategic Alignment#Corporate Objectives#Prioritization

Community Discussion

No community discussion yet for this question.

Full PFMP Practice