PFMP · Question #119

The relationship between the portfolio management plan and the communication plan is that the communication management plan:

The correct answer is A. is part of the portfolio management plan.. The communication management plan is a subsidiary component of the portfolio management plan, not a separate or equal document.

Portfolio Communication

Question

The relationship between the portfolio management plan and the communication plan is that the communication management plan:

Options

  • Ais part of the portfolio management plan.
  • Bis the overarching driver of how to communicate within the portfolio.
  • Cand portfolio management plan are unique, independent, and at the same level.
  • Dis completed first, followed by the development of the portfolio management plan.

How the community answered

(43 responses)
  • A
    91% (39)
  • B
    2% (1)
  • C
    7% (3)

Why each option

The communication management plan is a subsidiary component of the portfolio management plan, not a separate or equal document.

Ais part of the portfolio management plan.Correct

According to PMI's Standard for Portfolio Management, the portfolio management plan is the master planning document that encompasses multiple subsidiary plans, including the communications management plan. This hierarchical relationship means communication planning is governed within the broader portfolio management planning framework. The portfolio management plan is developed first, and subsidiary plans like the communication plan are created as components within it.

Bis the overarching driver of how to communicate within the portfolio.

The communication management plan is a subsidiary plan within the portfolio management plan and does not serve as the overarching driver of portfolio communications governance.

Cand portfolio management plan are unique, independent, and at the same level.

The communication management plan and portfolio management plan are not at the same level or independent; the former is a subsidiary of the latter.

Dis completed first, followed by the development of the portfolio management plan.

The portfolio management plan is developed before its subsidiary plans, including the communications plan, not the other way around.

Concept tested: Relationship between portfolio management plan and subsidiary plans

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Management Plan#Communication Management Plan#Planning Hierarchy#PMI Framework