Question
After three months, you have a list of all the program, project, and ongoing work being done in your 500-person Division of your State Government Agency. With this list, the next step is to:
Options
- ADetermine the prioritization model to follow
- BConvene a meeting of the Portfolio Review Board
- CAssess gaps in meeting the Agency's strategic objectives
- DPrepare a portfolio performance plan
Unlock PFMP to see the answer