PFMP · Question #734

PFMP Question #734: Real Exam Question with Answer & Explanation

The correct answer is A: Identifies internal and external dependencies. See the full explanation below for the reasoning.

Question

Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:

Options

  • AIdentifies internal and external dependencies
  • BServes as a master schedule to show the timing of approved components
  • CContains all the details of program and project roadmaps
  • DServes to identify issues