Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:

The correct answer is A. Identifies internal and external dependencies. A portfolio roadmap is a high-level strategic document that shows how components relate to each other and to the organization's strategic objectives over time. A key function is to identify internal dependencies (between portfolio components) and external dependencies (with…

Question

Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:

Options

  • AIdentifies internal and external dependencies
  • BServes as a master schedule to show the timing of approved components
  • CContains all the details of program and project roadmaps
  • DServes to identify issues

How the community answered

(37 responses)
  • A
    73% (27)
  • B
    8% (3)
  • C
    3% (1)
  • D
    16% (6)

Explanation

A portfolio roadmap is a high-level strategic document that shows how components relate to each other and to the organization's strategic objectives over time. A key function is to identify internal dependencies (between portfolio components) and external dependencies (with outside organizations, market conditions, or regulatory requirements). This is essential for sequencing and coordinating work. Option B is incorrect because the roadmap is not a detailed master schedule; schedules exist at the program and project level. Option C is incorrect because the portfolio roadmap deliberately omits granular details found in lower-level roadmaps. Option D (identifying issues) is not the roadmap's primary purpose-that belongs to risk and issue logs.