Each portfolio risk should have a designated person as its owner. As the portfolio manager assigns the owner, the main responsibility is to:
The correct answer is C. Monitor the situation as long as the risk is current. A risk owner's primary ongoing responsibility is to monitor the risk for as long as it remains active. Risk analysis (A) occurs before ownership is assigned. Implementing a response (B) is a reactive action triggered by the risk occurring, not the standing duty. Turning a threat
Question
Each portfolio risk should have a designated person as its owner. As the portfolio manager assigns the owner, the main responsibility is to:
Options
- AAnalyze the risk for its overall impact on portfolio success
- BDetermine an appropriate response and implement it as soon as the risk occurs
- CMonitor the situation as long as the risk is current
- DStrive to take a negative risk and turn it into a positive opportunity
How the community answered
(18 responses)- A6% (1)
- B11% (2)
- C78% (14)
- D6% (1)
Explanation
A risk owner's primary ongoing responsibility is to monitor the risk for as long as it remains active. Risk analysis (A) occurs before ownership is assigned. Implementing a response (B) is a reactive action triggered by the risk occurring, not the standing duty. Turning a threat into an opportunity (D) is a specific response strategy, not the core responsibility. Monitoring ensures the risk's status, probability, and impact are tracked continuously so timely action can be taken if conditions change.