Question
Recognizing that different components can have different types of risks, you decide to see how each risk affects the components. For example, assume you have identified a structural risk as overly ambitious plans and determine this risk affects three of the top five risks in your portfolio. You also have identified an environmental risk, in terms of whether the component will promote the organization's vision, which affects two components. Each component then has some other types of risks that affect it. From such an analysis you can see:
Options
- AGaps in the portfolio
- BCommon causes
- COverall portfolio risk impact
- DRebalancing needs