One of your component managers came to you to tell you about a risk affecting his component that will badly impact the component and might affect the portfolio. After assessment, the risk turned out…
The correct answer is D. Inform him that he does not need to worry, you will have a risk contingency reserve for his risk at. In portfolio risk management, risks with low probability but high impact are typically addressed at the portfolio level through a risk contingency reserve rather than at the component level. Because the probability is low, it is not cost-effective for the component manager to…
Question
One of your component managers came to you to tell you about a risk affecting his component that will badly impact the component and might affect the portfolio. After assessment, the risk turned out to be of low probability with high impact. What do you do as a portfolio manager?
Options
- AInform him to submit a change request to raise the component contingency because of this risk
- BInform the component manager to add the risk to the risk register and follow up on it closely
- CInform the component manager to add the risk to the risk register, assign a senior risk owner to it
- DInform him that he does not need to worry, you will have a risk contingency reserve for his risk at
How the community answered
(51 responses)- A8% (4)
- B14% (7)
- C4% (2)
- D75% (38)
Explanation
In portfolio risk management, risks with low probability but high impact are typically addressed at the portfolio level through a risk contingency reserve rather than at the component level. Because the probability is low, it is not cost-effective for the component manager to take active mitigation actions; however, because the impact is high, the portfolio manager must be prepared to absorb the consequences if the risk materializes. Maintaining a portfolio-level contingency reserve is the standard approach for handling these types of risks. This also avoids burdening the component with a change request (Option A) or over-assigning resources to a low-likelihood event.
Community Discussion
No community discussion yet for this question.