PFMP · Question #472
The portfolio strategic plan should contain a prioritization model or approach that guides the ongoing decisions as to which portfolio components should be added, terminated, or changed, as well as…
The correct answer is A. All of the options. A well-constructed portfolio prioritization model incorporates multiple dimensions to support balanced, strategic decision-making. ROI (Return on Investment) quantifies financial value; criteria to ensure alignment to strategic goals confirm that components support…
Question
The portfolio strategic plan should contain a prioritization model or approach that guides the ongoing decisions as to which portfolio components should be added, terminated, or changed, as well as prioritizes and balances the component mix over time. A simple prioritization model may be provided which contains
Options
- AAll of the options
- BROI
- CCriteria to ensure alignment to strategic goals
- DInvestment risks
How the community answered
(23 responses)- A87% (20)
- C9% (2)
- D4% (1)
Explanation
A well-constructed portfolio prioritization model incorporates multiple dimensions to support balanced, strategic decision-making. ROI (Return on Investment) quantifies financial value; criteria to ensure alignment to strategic goals confirm that components support organizational direction; and investment risks help weigh the probability and impact of uncertainty. Because all three elements - ROI, strategic alignment criteria, and investment risk - are standard components of a portfolio prioritization model per the PMI Standard for Portfolio Management, the correct answer is 'All of the options.'