PFMP · Question #473
After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in…
The correct answer is B. Portfolio updates. When a strategic change is finalized and affects portfolio component attributes (such as scope, cost, schedule, priority, or status of individual components), those attribute changes are recorded directly in the Portfolio document itself - referred to as 'Portfolio updates.'…
Question
After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in which you document these changes?
Options
- APortfolio Strategic Plan updates
- BPortfolio updates
- CPortfolio Management Plan updates
- DPortfolio Process Assets updates
How the community answered
(34 responses)- A3% (1)
- B88% (30)
- C3% (1)
- D6% (2)
Explanation
When a strategic change is finalized and affects portfolio component attributes (such as scope, cost, schedule, priority, or status of individual components), those attribute changes are recorded directly in the Portfolio document itself - referred to as 'Portfolio updates.' The Portfolio document contains the list and key attributes of all components. The Portfolio Management Plan governs how management is conducted (processes, governance), not individual component attribute data, making 'Portfolio updates' the correct output artifact.
Topics
Community Discussion
No community discussion yet for this question.