PFMP · Question #473

After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in…

The correct answer is B. Portfolio updates. When a strategic change is finalized and affects portfolio component attributes (such as scope, cost, schedule, priority, or status of individual components), those attribute changes are recorded directly in the Portfolio document itself - referred to as 'Portfolio updates.'…

Portfolio Governance

Question

After a strategic change is managed and finalized, you as a portfolio manager, are expected to document changes to the portfolio components attributes. Which of the following is the document in which you document these changes?

Options

  • APortfolio Strategic Plan updates
  • BPortfolio updates
  • CPortfolio Management Plan updates
  • DPortfolio Process Assets updates

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    88% (30)
  • C
    3% (1)
  • D
    6% (2)

Explanation

When a strategic change is finalized and affects portfolio component attributes (such as scope, cost, schedule, priority, or status of individual components), those attribute changes are recorded directly in the Portfolio document itself - referred to as 'Portfolio updates.' The Portfolio document contains the list and key attributes of all components. The Portfolio Management Plan governs how management is conducted (processes, governance), not individual component attribute data, making 'Portfolio updates' the correct output artifact.

Topics

#Portfolio Documentation#Portfolio Components#Portfolio Governance#Strategic Change Management