PFMP Question #471: Real Exam Question with Answer & Explanation

The correct answer is D: Internal Stakeholders. See the full explanation below for the reasoning.

Portfolio Governance

Question

The interest, influence, and communication needs of business operational stakeholders who are looking to ensure alignment between portfolio components, while minimizing negative impact and maximizing positive benefits of all portfolio-managed changes to their business operations, relate to which type of stakeholders?

Options

  • AInternal and External Stakeholders
  • BExternal Stakeholders
  • CDoes not relate to stakeholders
  • DInternal Stakeholders

Topics

#Stakeholder Management#Internal Stakeholders#Portfolio Governance#Business Alignment

Community Discussion