PFMP · Question #379

PFMP Question #379: Real Exam Question with Answer & Explanation

The correct answer is D: Continue your work and perform the manage supply and demand process. See the full explanation below for the reasoning.

Portfolio Performance

Question

As a portfolio manager you need to continuously balance the need and requirements with the available resources to maintain a balanced portfolio and portfolio resources in order to optimize delivery. One of your key stakeholders came to you asking to skip the manage supply and demand process as you have already prioritized and allocated resources through the strategic management and the governance processes. As a portfolio manager you should

Options

  • ARaise this to the steering committee for approval
  • BSkip the step as the stakeholder is correct and you can always re-do the process as part of
  • CContinue work and ignore the stakeholder's request as this stakeholder is known to resist change
  • DContinue your work and perform the manage supply and demand process

Topics

#Portfolio Resource Management#Manage Supply and Demand#Portfolio Processes#Portfolio Performance