The correct answer is A: To know about the portfolio changes, risks and issues that may affect their components. See the full explanation below for the reasoning.
Communications Management
Question
While managing portfolio communications, the portfolio manager needs to account for the communication needs of the component teams in order for them to stay in the loop of the big picture. Which of the following can be of interest to this group of stakeholders?
Options
- ATo know about the portfolio changes, risks and issues that may affect their components
- BTo be informed regularly of the portfolio progress so they can adjust their work accordingly
- CTo be informed of all portfolio changes so they can assess which changes affect their
- DTo know about the portfolio changes, risks and issues that may affect their components, and to
Topics
#Portfolio Communication#Stakeholder Management#Information Needs#Portfolio Monitoring