After reviewing the portfolio performance reports, which section of the portfolio management plan should a portfolio manager review in order to follow the defined process to approve, execute, and…

The correct answer is B. Change control and management. The change control and management section of the portfolio management plan defines the approved process for handling schedule and budget adjustments.

Governance

Question

After reviewing the portfolio performance reports, which section of the portfolio management plan should a portfolio manager review in order to follow the defined process to approve, execute, and manage schedule and budget adjustments?

Options

  • AManaging strategic change
  • BChange control and management
  • CPerformance management planning
  • DPortfolio oversight

How the community answered

(15 responses)
  • B
    87% (13)
  • C
    7% (1)
  • D
    7% (1)

Why each option

The change control and management section of the portfolio management plan defines the approved process for handling schedule and budget adjustments.

AManaging strategic change

Managing strategic change addresses how the portfolio responds to shifts in organizational strategy, not routine schedule and budget adjustment procedures.

BChange control and managementCorrect

The change control and management section of the portfolio management plan specifically documents the defined process for submitting, reviewing, approving, and executing changes to portfolio components, including schedule and budget adjustments. After reviewing performance reports that reveal variances, this is the section a portfolio manager must consult to ensure any corrective actions follow the established governance process. It provides the procedural authority for making authorized adjustments.

CPerformance management planning

Performance management planning defines how portfolio performance will be measured and reported, not the process for approving and executing adjustments.

DPortfolio oversight

Portfolio oversight covers governance roles and responsibilities at a high level and does not provide the specific procedural steps for approving schedule and budget changes.

Concept tested: Change control process in portfolio management plan

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management