MB6-700 · Question #22
You define project requirements in the work breakdown structure. What do the Importance settings determine?
The correct answer is C. Relative importance between activity requirements. See the full explanation below for the reasoning.
Question
You define project requirements in the work breakdown structure. What do the Importance settings determine?
Options
- ARelative importance between tasks
- BRelative importance between projects
- CRelative importance between activity requirements
- DRelative importance of schedule versus activity requirements
How the community answered
(26 responses)- A4% (1)
- B8% (2)
- C77% (20)
- D12% (3)