You set up a new internal project. You need to manually create a hierarchical representation of the activities for the project. Which form should you use?
The correct answer is D. Work breakdown structure. See the full explanation below for the reasoning.
Question
You set up a new internal project. You need to manually create a hierarchical representation of the activities for the project. Which form should you use?
Options
- AActivities
- BAssign resources
- CWork breakdown structure template
- DWork breakdown structure
How the community answered
(28 responses)- A4% (1)
- B11% (3)
- C7% (2)
- D79% (22)