MB6-700 · Question #21

MB6-700 Question #21: Real Exam Question with Answer & Explanation

The correct answer is D. Work breakdown structure. See the full explanation below for the reasoning.

Question

You set up a new internal project. You need to manually create a hierarchical representation of the activities for the project. Which form should you use?

Options

  • AActivities
  • BAssign resources
  • CWork breakdown structure template
  • DWork breakdown structure

Community Discussion

No community discussion yet for this question.