MB6-700 · Question #21
MB6-700 Question #21: Real Exam Question with Answer & Explanation
The correct answer is D. Work breakdown structure. See the full explanation below for the reasoning.
Question
You set up a new internal project. You need to manually create a hierarchical representation of the activities for the project. Which form should you use?
Options
- AActivities
- BAssign resources
- CWork breakdown structure template
- DWork breakdown structure