The correct answer is C. Transactions posted to the project. See the full explanation below for the reasoning.

Question

Based on which method do time and material projects create invoices?

Options

  • AMonthly payments
  • BPredefined milestones in the project
  • CTransactions posted to the project
  • DProject phases