MB6-700 · Question #6
You set up a new internal project that includes work in process (WIP). You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the…
The correct answer is D. Project groups. See the full explanation below for the reasoning.
Question
You set up a new internal project that includes work in process (WIP). You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet. Which form should you use to specify that each type of cost will be posted to balance accounts?
Options
- ALedger updates
- BLedger posting setup
- CPost costs
- DProject groups
How the community answered
(49 responses)- A2% (1)
- B12% (6)
- C4% (2)
- D82% (40)