MB6-700 · Question #6

You set up a new internal project that includes work in process (WIP). You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the…

The correct answer is D. Project groups. See the full explanation below for the reasoning.

Question

You set up a new internal project that includes work in process (WIP). You need to ensure that the actual project costs for hours,expenses,and items are posted to a WIP financial account on the balance sheet. Which form should you use to specify that each type of cost will be posted to balance accounts?

Options

  • ALedger updates
  • BLedger posting setup
  • CPost costs
  • DProject groups

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    12% (6)
  • C
    4% (2)
  • D
    82% (40)