Microsoft
MB6-700 · Question #14
Which two items are determined by the cost templates for advanced fixed-price projects? (Each correct answer presents part of the solution. Choose two.)
The correct answer is C. Whether to calculate the degree of completion on the posted amount or quantity D. The categories included in calculating the degree of completion. See the full explanation below for the reasoning.
Question
Which two items are determined by the cost templates for advanced fixed-price projects? (Each correct answer presents part of the solution. Choose two.)
Options
- AThe amount of hours that can be posted for advanced fixed-price projects
- BThe amount of expenses that can be posted for advanced fixed-price projects
- CWhether to calculate the degree of completion on the posted amount or quantity
- DThe categories included in calculating the degree of completion
How the community answered
(37 responses)- A5% (2)
- B16% (6)
- C78% (29)
Community Discussion
No community discussion yet for this question.