MB6-700 · Question #37

For which two project types can on-account forecasting be used? (Each correct answer presents part of the solution. Choose two.)

The correct answer is B. fixed-price D. time and material. See the full explanation below for the reasoning.

Question

For which two project types can on-account forecasting be used? (Each correct answer presents part of the solution. Choose two.)

Options

  • Acost
  • Bfixed-price
  • Cinvestment
  • Dtime and material

How the community answered

(66 responses)
  • A
    17% (11)
  • B
    74% (49)
  • C
    9% (6)