You are managing business closures in Dynamics CRM. You configure business closure days for your company. You have 50 managers who belong to a resource group named Managers. You need to ensure that…
The correct answer is B. the closure for the CRM organization. See the full explanation below for the reasoning.
Question
You are managing business closures in Dynamics CRM. You configure business closure days for your company. You have 50 managers who belong to a resource group named Managers. You need to ensure that the managers can be scheduled for activities anytime, including during the business closure days. All other resources must be prevented from being scheduled on the business closure days. What should you configure?
Options
- Athe user records
- Bthe closure for the CRM organization
- Cthe selection rules
- Dthe record for the Managers resource group
How the community answered
(16 responses)- A6% (1)
- B88% (14)
- D6% (1)
Community Discussion