MB2-714 · Question #29
MB2-714 Question #29: Real Exam Question with Answer & Explanation
Sign in or unlock MB2-714 to reveal the answer and full explanation for question #29. The question stem and answer options stay visible for context.
Question
You have an equipment resource for a forklift. Several scheduling activities are configured to use the forklift. The forklift breaks down and is sent for repairs. You set the work hours for the forklift to unavailable. You need to identify what will occur to the scheduling activities that require the forklift. What should you identify?
Options
- AThe scheduling activities will be added to a queue.
- BThe scheduling activities will continue as scheduled.
- CThe scheduling activities will be scheduled automatically for the next available time.
- DThe scheduling activities will be deactivated.