MB-335 · Question #127
A vendor plans to supply replacements for a product that they manufactured. The cost associated with manufacturing most components of the replacement product differ from costs associated with the…
The correct answer is C. Multilevel. You've hit your limit · resets 4am (America/New_York)
Configure production prerequisites
Question
A vendor plans to supply replacements for a product that they manufactured. The cost associated with manufacturing most components of the replacement product differ from costs associated with the original product. You need to plan for the new cost of the item in determining the sales price. Which costing version explosion mode should you use?
Options
- AAccording to BOM line type
- BSingle level
- CMultilevel
- DMake to Order
How the community answered
(27 responses)- A15% (4)
- B4% (1)
- C74% (20)
- D7% (2)
Explanation
You've hit your limit · resets 4am (America/New_York)
Topics
#costing version#multilevel explosion#BOM cost rollup#sales price