The correct answer is A. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.. See the full explanation below for the reasoning.
Question
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup: - The setup uses a Lean schedule group with a throughput ratio = 2. - The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1. - The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day). - The throughput is 10 per hour. You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?
Options
- ACreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
- BCreate a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1.
- CCreate a route with a runtime = 10, a process quantity = 6, and the operation's hours/time = 1.
- DCreate a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1.