ITSM20F.EN · Question #77
A number of new PCs have been installed at a company's offices. For which activity was the Configuration management process responsible?
The correct answer is D. Recording data regarding the PCs. You've hit your weekly limit · resets 5am (America/New_York)
Control processes
Question
A number of new PCs have been installed at a company's offices. For which activity was the Configuration management process responsible?
Options
- AEstablishing the correct links in the Local Area Network
- BInstalling software
- CMaking available the necessary user's manuals
- DRecording data regarding the PCs
How the community answered
(55 responses)- A5% (3)
- B4% (2)
- C13% (7)
- D78% (43)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#configuration management#CI records#asset recording#CMS