ITIL-4-CDS · Question #75
ITIL-4-CDS Question #75: Real Exam Question with Answer & Explanation
The correct answer is B. Establish a single, cross-functional Kanban board with work-in-progress (WIP) limits applied. A unified Kanban board with WIP limits visualizes all incoming work, highlights interteam dependencies, enforces flow control, and prevents any one queue from becoming overloaded. This approach drives collaboration, reduces handover delays, and makes prioritization transparent ac
Question
Options
- AConduct a detailed value stream mapping exercise to identify end-to-end process bottlenecks and
- BEstablish a single, cross-functional Kanban board with work-in-progress (WIP) limits applied
- CImplement a RACI matrix for all migration and support activities to clarify roles, responsibilities,
- DPrioritize support tickets and migration tasks strictly according to their arrival time to ensure
Explanation
A unified Kanban board with WIP limits visualizes all incoming work, highlights interteam dependencies, enforces flow control, and prevents any one queue from becoming overloaded. This approach drives collaboration, reduces handover delays, and makes prioritization transparent across development, operations, and support.