When a new service is being planned, Service Level Management needs to ensure that existing performance levels of other IT services will not be unduly impacted. From which process will Service Level…

The correct answer is B. Capacity Management. See the full explanation below for the reasoning.

Question

When a new service is being planned, Service Level Management needs to ensure that existing performance levels of other IT services will not be unduly impacted. From which process will Service Level Management require input?

Options

  • AAvailability Management
  • BCapacity Management
  • CFinancial Management for IT Services
  • DIT Service Continuity Management

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    72% (21)
  • C
    17% (5)