A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?
The correct answer is B. Fixed price (FP). ISEB ISEB-PM1 Exam
Business Concepts
Question
A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?
Options
- ACost reimbursable (CR)
- BFixed price (FP)
- CTime and material (T&M)
- DCost plus fixed fee (CPFF)
How the community answered
(28 responses)- A4% (1)
- B82% (23)
- C4% (1)
- D11% (3)
Explanation
ISEB ISEB-PM1 Exam
Topics
#contract types#fixed price#procurement#project planning