ISEB-PM1 · Question #63

A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?

The correct answer is B. Fixed price (FP). ISEB ISEB-PM1 Exam

Business Concepts

Question

A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements. Which is the BEST contract to choose?

Options

  • ACost reimbursable (CR)
  • BFixed price (FP)
  • CTime and material (T&M)
  • DCost plus fixed fee (CPFF)

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    82% (23)
  • C
    4% (1)
  • D
    11% (3)

Explanation

ISEB ISEB-PM1 Exam

Topics

#contract types#fixed price#procurement#project planning