ISEB-PM1 · Question #613

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

The correct answer is C. conceptual. You've hit your weekly limit · resets 5am (America/New_York)

Risk Management

Question

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

Options

  • ABoth 1) conceptual, and 2)post project evaluation
  • Bcut-over
  • Cconceptual
  • Dexecution
  • Epost project evaluation

How the community answered

(25 responses)
  • A
    4% (1)
  • C
    76% (19)
  • D
    12% (3)
  • E
    8% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#project risk#project phases#uncertainty#risk lifecycle