Question
You are a project manager for an engineering company. Your company won the bid to add ramp- metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves ISEB ISEB-PM1 Exam digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. Which of the following is not a valid option?
Options
- AYou document the poor performance in written form and send the correspondence to the
- BYou terminate the contract for poor performance and submit a change request through
- CYou agree to meet with the subcontractor to see whether a satisfactory solution can be
- DYou submit a change request through Contract Administration demanding that the