You are a project manager for an engineering company. Your company won the bid to add ramp- metering lights to several on-ramps along a stretch of highway at the south end of the city. You…

The correct answer is D. You submit a change request through Contract Administration demanding that the. You've hit your weekly limit · resets 5am (America/New_York)

Project Control

Question

You are a project manager for an engineering company. Your company won the bid to add ramp- metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves ISEB ISEB-PM1 Exam digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. Which of the following is not a valid option?

Options

  • AYou document the poor performance in written form and send the correspondence to the
  • BYou terminate the contract for poor performance and submit a change request through
  • CYou agree to meet with the subcontractor to see whether a satisfactory solution can be
  • DYou submit a change request through Contract Administration demanding that the

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    5% (1)
  • C
    5% (1)
  • D
    79% (15)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#contract administration#subcontractor management#poor performance#procurement