The correct answer is E. 1) Smoothes out resource requirements by rescheduling activities within their float time, or 2). See the full explanation below for the reasoning.
Question
Resource leveling _____.
Options
- AAttempts to reduce resource requirements within a constraint on project duration
- BSmoothes out resource requirements by rescheduling activities within their float time.
- CAllocates resources to activities to find shortest schedule within fixed resource limits.
- DSmooths out resource requirements by substituting activities with unassigned resources.
- E
- Smoothes out resource requirements by rescheduling activities within their float time, or 2)