ISEB-PM1 · Question #612
Resource leveling _____.
The correct answer is E. 1) Smoothes out resource requirements by rescheduling activities within their float time, or 2). You've hit your weekly limit · resets 5am (America/New_York)
Resource Management
Question
Resource leveling _____.
Options
- AAttempts to reduce resource requirements within a constraint on project duration
- BSmoothes out resource requirements by rescheduling activities within their float time.
- CAllocates resources to activities to find shortest schedule within fixed resource limits.
- DSmooths out resource requirements by substituting activities with unassigned resources.
- E
- Smoothes out resource requirements by rescheduling activities within their float time, or 2)
How the community answered
(43 responses)- A16% (7)
- B2% (1)
- C5% (2)
- D7% (3)
- E70% (30)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#resource leveling#float time#resource smoothing#schedule optimization