Question

Resource leveling _____.

Options

  • AAttempts to reduce resource requirements within a constraint on project duration
  • BSmoothes out resource requirements by rescheduling activities within their float time.
  • CAllocates resources to activities to find shortest schedule within fixed resource limits.
  • DSmooths out resource requirements by substituting activities with unassigned resources.
  • E
    1. Smoothes out resource requirements by rescheduling activities within their float time, or 2)