ISEB-PM1 · Question #528
Which of the following describes the purpose of the quality control process?
The correct answer is C. To assess performance and recommend necessary changes. Quality Control (QC) is the monitoring and inspection process that measures actual performance against standards, then recommends corrective actions when deviations are found - making C correct. It's the "checking" phase, not the "defining" or "planning" phase. A is wrong…
Question
Which of the following describes the purpose of the quality control process?
Options
- ATo identify quality requirements of the project
- BTo identify ineffective processes and eliminate them
- CTo assess performance and recommend necessary changes
- DTo ensure quality standards are used
How the community answered
(45 responses)- A16% (7)
- B9% (4)
- C71% (32)
- D4% (2)
Explanation
Quality Control (QC) is the monitoring and inspection process that measures actual performance against standards, then recommends corrective actions when deviations are found - making C correct. It's the "checking" phase, not the "defining" or "planning" phase.
- A is wrong because identifying quality requirements happens in Quality Planning, not Quality Control.
- B is wrong because eliminating ineffective processes is the goal of Quality Assurance (QA), which audits processes organization-wide.
- D is wrong because ensuring quality standards are applied is also a QA responsibility - QC measures results against those standards rather than enforcing their use.
Memory tip: Think of QC as a report card - it evaluates outputs already produced, compares them to expectations, and flags what needs to change. QA is the teacher setting the curriculum; QC is the grader marking the homework.
Topics