Which quality assurance tool and technique confirms the implementation of approved change requests, corrective actions, defect repairs, and preventive actions?

The correct answer is C. Quality audits. Quality audits are structured, independent reviews that verify whether project activities comply with organizational and project policies - specifically confirming that approved change requests, corrective actions, defect repairs, and preventive actions have actually been…

Quality Management

Question

Which quality assurance tool and technique confirms the implementation of approved change requests, corrective actions, defect repairs, and preventive actions?

Options

  • AQuality checklists
  • BQuality metrics
  • CQuality audits
  • DProcess analysis

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    9% (2)
  • C
    74% (17)
  • D
    4% (1)

Explanation

Quality audits are structured, independent reviews that verify whether project activities comply with organizational and project policies - specifically confirming that approved change requests, corrective actions, defect repairs, and preventive actions have actually been implemented as intended. Distractors fall short for distinct reasons: quality checklists are simple structured lists used to verify that a set of steps has been performed, not to confirm implementation of change-related actions; quality metrics are measurable values (defect rates, test coverage) used to track performance over time, not to verify compliance; process analysis examines processes to identify improvements and root causes, not to confirm that specific approved actions were carried out. Memory tip: think of an audit like an inspector's visit - its job is to confirm "did you actually do what you said you'd do?" which maps directly to verifying implemented changes, repairs, and preventive actions.

Topics

#quality audits#quality assurance#change requests#corrective actions