A quality management plan is created during which of the following?

The correct answer is B. Plan Quality. You've hit your session limit · resets 10:20pm (America/New_York)

Quality Management

Question

A quality management plan is created during which of the following?

Options

  • AProject Executing
  • BPlan Quality
  • CPerform Quality Assurance
  • DPerform Quality Control

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    71% (25)
  • C
    17% (6)
  • D
    3% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#quality management plan#Plan Quality#quality planning process