A quality management plan is created during which of the following?
The correct answer is B. Plan Quality. You've hit your session limit · resets 10:20pm (America/New_York)
Quality Management
Question
A quality management plan is created during which of the following?
Options
- AProject Executing
- BPlan Quality
- CPerform Quality Assurance
- DPerform Quality Control
How the community answered
(35 responses)- A9% (3)
- B71% (25)
- C17% (6)
- D3% (1)
Explanation