ISEB-PM1 · Question #4
A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked…
The correct answer is C. A project manager must be able to weigh the benefits of the change versus the costs and. Option C is correct because integrated change control requires a project manager to evaluate the benefits, costs, and risks of any proposed change before granting approval - requesting a written report is not bureaucratic obstruction, it is proper process. Without a documented…
Question
A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change. What is the MOST appropriate advice for the situation?
Options
- AThe project manager is being unreasonable and should do that kind of work herself.
- BRemind the project manager that the benefit cost analysis for the project was done during
- CA project manager must be able to weigh the benefits of the change versus the costs and
- DThe team member should do what was asked because this sort of information must be given to
How the community answered
(66 responses)- A3% (2)
- B8% (5)
- C73% (48)
- D17% (11)
Explanation
Option C is correct because integrated change control requires a project manager to evaluate the benefits, costs, and risks of any proposed change before granting approval - requesting a written report is not bureaucratic obstruction, it is proper process. Without a documented cost-benefit analysis, the PM cannot make an informed decision or present the change to a change control board.
Why A is wrong: The PM is acting correctly by requiring documentation; asking a requester to justify a change is standard practice, not laziness or unreasonableness.
Why B is wrong: The original benefit-cost analysis covered the project baseline, not every subsequent change request - each change needs its own evaluation because it carries its own unique costs and risks.
Why D is wrong: While complying is the right action, D frames it as mere obedience ("do what was asked") rather than grounding it in the professional principle that change analysis is a required input to any approval decision.
Memory tip: Think of integrated change control as a gate: no change passes without a cost-benefit ticket. Whoever proposes the change provides the ticket - the PM's job is to evaluate it, not write it.