ISEB-PM1 · Question #4

A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked…

The correct answer is C. A project manager must be able to weigh the benefits of the change versus the costs and. Option C is correct because integrated change control requires a project manager to evaluate the benefits, costs, and risks of any proposed change before granting approval - requesting a written report is not bureaucratic obstruction, it is proper process. Without a documented…

Project Control

Question

A project team member tells you that she went to her project manager with a good idea for a useful change to the project. Instead of giving her approval to make the change, the project manager asked her to write a report describing the benefits of the change. What is the MOST appropriate advice for the situation?

Options

  • AThe project manager is being unreasonable and should do that kind of work herself.
  • BRemind the project manager that the benefit cost analysis for the project was done during
  • CA project manager must be able to weigh the benefits of the change versus the costs and
  • DThe team member should do what was asked because this sort of information must be given to

How the community answered

(66 responses)
  • A
    3% (2)
  • B
    8% (5)
  • C
    73% (48)
  • D
    17% (11)

Explanation

Option C is correct because integrated change control requires a project manager to evaluate the benefits, costs, and risks of any proposed change before granting approval - requesting a written report is not bureaucratic obstruction, it is proper process. Without a documented cost-benefit analysis, the PM cannot make an informed decision or present the change to a change control board.

Why A is wrong: The PM is acting correctly by requiring documentation; asking a requester to justify a change is standard practice, not laziness or unreasonableness.

Why B is wrong: The original benefit-cost analysis covered the project baseline, not every subsequent change request - each change needs its own evaluation because it carries its own unique costs and risks.

Why D is wrong: While complying is the right action, D frames it as mere obedience ("do what was asked") rather than grounding it in the professional principle that change analysis is a required input to any approval decision.

Memory tip: Think of integrated change control as a gate: no change passes without a cost-benefit ticket. Whoever proposes the change provides the ticket - the PM's job is to evaluate it, not write it.

Topics

#change control#benefit cost analysis#change request process