A work authorization system can be used to:

The correct answer is B. Manage when and in what sequence work is done. A work authorization system (WAS) is a formal procedure used to sanction project work, ensuring it begins at the right time and in the right order - making B the only complete, accurate answer. Option A is incorrect because assigning who performs work belongs to the resource…

Project Control

Question

A work authorization system can be used to:

Options

  • AManage who does each activity.
  • BManage when and in what sequence work is done.
  • CManage when each activity is done.
  • DManage who does each activity and when it is done.

How the community answered

(47 responses)
  • A
    9% (4)
  • B
    70% (33)
  • C
    17% (8)
  • D
    4% (2)

Explanation

A work authorization system (WAS) is a formal procedure used to sanction project work, ensuring it begins at the right time and in the right order - making B the only complete, accurate answer. Option A is incorrect because assigning who performs work belongs to the resource management plan and the Responsibility Assignment Matrix (RACI), not the WAS. Option C is a partial truth - timing is involved, but it omits sequencing, which is the other half of what a WAS controls; a half-right answer is a wrong answer on the exam. Option D combines the correct "when" with the incorrect "who," making it a trap for test-takers who confuse resource assignment with work authorization.

Memory tip: Think of a WAS as a traffic light system for tasks - it controls not just when the green light turns on, but which light goes green first, emphasizing sequence and timing together.