A project manager has made a change to the project. What should she do NEXT?

The correct answer is B. Revise the project management plan and/or project documents. See the full explanation below for the reasoning.

Project Control

Question

A project manager has made a change to the project. What should she do NEXT?

Options

  • AAssign resources.
  • BRevise the project management plan and/or project documents.
  • CEvaluate impact.
  • DRequest change control board involvement.

How the community answered

(16 responses)
  • A
    13% (2)
  • B
    75% (12)
  • C
    6% (1)
  • D
    6% (1)

Topics

#change management#project management plan#change process