A project manager has made a change to the project. What should she do NEXT?
The correct answer is B. Revise the project management plan and/or project documents. See the full explanation below for the reasoning.
Project Control
Question
A project manager has made a change to the project. What should she do NEXT?
Options
- AAssign resources.
- BRevise the project management plan and/or project documents.
- CEvaluate impact.
- DRequest change control board involvement.
How the community answered
(16 responses)- A13% (2)
- B75% (12)
- C6% (1)
- D6% (1)
Topics
#change management#project management plan#change process